Pit & Foundation

To realise the construction pit, a hole was dug measuring approximately 50 metres by 50 metres and 21 metres deep. This was done in several stages. First, trenches were dug 1,5 metres wide, into which concrete was poured to realise the diaphragm walls. These walls were anchored, and within these walls, 380 bored piles were placed, after which the soil was excavated and underwater concrete was poured to hold the empty pit in place and to base the reactor on later. The works were carried out by BESIX and completed in May 2025. 

  • Preparation of the work area.
  • Installation of diaphragm walls.
  • Placement of capping beams.
  • Anchoring.
  • Excavation of the construction pit.
  • Drilling SI piles.
  • Application of soil improvement.
  • Application of underwater concrete.
  • Pumping out water from the construction pit.
  • Installation of the bearing slab.
  • Cleaning of the work area.
480x530
480x530

,,Completion of the Pit & Foundation has laid the foundation for the next phase of construction, a significant step forward on the path to realizing the PALLAS-reactor.” - Peter Dijk, Director PALLAS Programme